DEA&DP REF NUMBER: 16/3/3/1/D2/19/0003/24
PLEASE NOTE: The Draft Basic Assessment Report for the above-mentioned project is available for a 30-day review and commenting period till 15 March 2024. Kindly forward your written comments to Michael Bennett at email: michael@sescc.net, fax: 086 575 2869, or postal address: PO Box 9087, George, 6530 on or before 15 March 2024.
Schaapkop Pipeline draft BAR – 17 January 2024
Appendix A3 – Pipeline Route GPS points
Appendix D – Critical Biodiversity Areas Map
Appendix E22 – Ackn+Comment.PP-plan and PP Plan
Appendix G1 – Botanical assessment Schaapkop sewer 2 – Jan 24
Appendix G2 – Aquatic assessment report_Schaapkop Rising Main Sewer Pipeline_V3_2024
Appendix G2.1 – WULA information
Appendix G3 – Terrestrial – updated 17 January 2024
Appendix H – draft EMPr – 17 January 2024
Appendix I – STR—2023-05-17 09-32
Appendix J – Engineering – Proposed Construction Methodology